
Pass L4M3 Brain Dump Updated Certification Sample Questions
Online L4M3 Test Brain Dump Question and Test Engine
CIPS L4M3 Certification Exam covers a range of topics related to commercial contracting, including the principles of contract law, procurement and contract management, contract negotiation, risk management, and dispute resolution. L4M3 exam is designed to be challenging and comprehensive, ensuring that candidates have a thorough understanding of the subject matter.
NEW QUESTION # 92
Which of the following indicates the ratio between profit and costs?
- A. Margin
- B. Gearing
- C. Liquidity
- D. Mark-up
Answer: D
Explanation:
Mark up is the profit as a percentage of total costs.
LO 3, AC 3.3
NEW QUESTION # 93
Which of the following is used to detail the complex matter that may be verbiage to the main document?
- A. Contract variation
- B. Schedule
- C. Subcontracting
- D. Standard terms and conditions
Answer: B
Explanation:
Without further explanation, a schedule may be deemed to form an integral part of the obligations of either or both parties. Obviously, the scope or binding nature of such schedule depends on the way it is referred to in the obligatory language of the main agreement. Accordingly, merely attaching the general terms and conditions of sale without explaining to which part of the sale they apply or which provisions apply does not subject a sale pursuant to the body text of the agreement to those general terms and conditions.
Subcontracting is the practice of assigning, or outsourcing, part of the obligations and tasks under a contract to another party known as a subcontractor.
Reference:
- Schedules, annexes and exhibits
- CIPS study guide page 22-26
LO 1, AC 1.1
NEW QUESTION # 94
Which of the following is an example of liquidated damages clause?
1. "In the event of a delay to the Offshore Installation Completion Date as per the Contract Schedule for which Contractor is solely responsible, Contractor shall pay to Company 0.25% per day of delay, subject to a maximum of 10% of the Initial Contract Price."
2. "If Seller breaches its obligation to deliver goods in accordance with the schedule provided for in this contract, Seller shall pay Buyer $x per day for each day of delay"
3. "The Contractor shall defend and hold the Buyer, its officers, officials, employees and volunteers harmless from any and all claims, injuries, damages, losses or suits including attorney fees, arising out of or in connection with the performance of this Agreement, except for injuries and damages caused by the sole negligence of the Buyer."
4. "The contract is subjected to delay remedies. The amount will be agreed by both parties during the delivery"
- A. 1 and 3 only
- B. 1 and 2 only
- C. 3 and 4 only
- D. 2 and 4 only
Answer: B
Explanation:
Liquidated damages, also referred to as "liquidated and ascertained damages" (LADs) are damages whose amount the parties designate during the formation of a contract[2] for the injured party to collect as compensation upon a specific breach (e.g. late performance). In supply contracts and work contracts, the liquidated damages clause often take form as known damages to be paid per day delayed. Number 1 and 2 are examples of this clause.
Reference:
- Liquidated damages
- CIPS study guide 158-159
LO 3, AC 3.2
NEW QUESTION # 95
Which of the following is the term that describes an item bought for a single and non-recurring use or purpose?
- A. Call-off purchase
- B. Operational purchase
- C. Stock purchase
- D. Ad-hoc purchase
Answer: D
Explanation:
Ad-hoc purchase is the item bought for a single and non-recurring use or purpose.
A call-off contract, also known as a blanket order, is a purchase order which enables bulk orders over a period of time.
Operational procurement refers to the procurement of goods and services that are required to sustain an organization's day-to-day business operations.
Reference:
LO 1, AC 1.3
NEW QUESTION # 96
A service contract is going to be expired, which data source is good to create specifications for ITT?
1. Incumbent supplier
2. Maintenance services
3. Alternative supplier
4. User's knowledge
- A. 1, 2 and 3
- B. 1, 3 and 4
- C. 2, 3 and 4
- D. 1, 2 and 4
Answer: B
Explanation:
There are a number of shortcuts that can be taken when drafting the specification. These include the following:
- The use of brand names
- The use of recognised standards
- The use of samples
- Information and knowledge from users/other buyers: Drafting a specification should naturally include those already used within the organisation itself, but also variants used by other companies in the same sector and other companies in different sectors
- Information from suppliers: suppliers will always be willing to assist in specification development, as this this one way in which they can seek to influence the design to favour their own products.
Reference:
LO 2, AC 2.1
NEW QUESTION # 97
Express terms in a contract are stated in which of the following? Select TWO that apply
- A. Trade customs
- B. Writing form
- C. Statutes
- D. Orality
- E. Idea
Answer: B,D
Explanation:
Express terms are the terms of the agreement which are expressly agreed between the parties. Ideally, they will be written down in a contract between the parties but where the contract is agreed verbally, they will be the terms discussed and agreed between the parties.
Implied terms are terms implied into the contract by the courts. They are not expressly set out in the contract but are taken to be as effective as if they were and as if they had been included from day one of the contract. The express terms and any implied terms together create the legally binding obligations on the parties.
Reference:
- Contracts: Express and Implied Terms
- CIPS study guide page 126-132
LO 3, AC 3.1
NEW QUESTION # 98
Which of the following are likely to be advantages of using invitation to tender? Select TWO that apply:
Short turnaround times
- A. Reducing risks of bribery and corruption
- B. Driving forward planning culture
- C. Lower administration costs
- D. Quick implementation
Answer: A,B
Explanation:
Advantages of using invitation to tender may be as below:
No Nepotism: Tenders or bids are evaluated on the basis of certain predetermined criteria, such as price, quality and value for money. In other words, the firm offering the highest quality product or service at the lowest price point would win the contract. As most tender documents are opened and evaluated in a public process, I think that there remains little room for nepotism or favoritism of any kind.
Value for Money: From the perspective of the client, tenders offer the greatest value for the amount of money spent. This is due to the fact that the client can choose from a wide pool of potential suppliers to select the ones that can produce the highest quality product or service at the lowest price point. This allows the company, establishment or organization to save money without having to compromise on quality. Therefore, despite being quite time consuming, tendering is, in my opinion, a profitable long-term process from an organization's point of view.
Encourages Competition: The process of tendering helps promote a competitive market. This is because a number of potential contractors, firms or suppliers get a chance to bid for every project. And because selection depends on quality and price, every bidder tries to reduce operational inefficiencies and redundancies as much as possible in order to lower expenses and improve quality. This entire process encourages healthy competition in the market and prevents complacency and laziness, which in turn provides a boost to innovation and new ideas.
Easier Entry: The system of tendering makes it easier and simpler for new firms to enter the market or even a particular industry. This is due to the fact that contracts under this system are awarded on the basis of predetermined, objective criteria. As a result, even a firm that is a new entrant to the market, having no connections or contacts in the industry, can win a prestigious and lucrative contract by providing the highest value for the client's money. This process therefore helps new firms to quickly get a foothold in the market or industry, thus significantly lowering the traditional barriers to entry.
Reference:
- Characteristics and Benefits of the Tendering Process
- CIPS study guide page 6-8
LO 1, AC 1.1
NEW QUESTION # 99
XYZ Ltd and Engineer Corp signed a long-term supply contract in which both parties had agreed on performance targets. Recently, due to increased customer demands, XYZ Ltd realises that they should make changes to the contract with Engineer Corp with regards to performance management. These changes are approved and signed by both the buyer and seller. The changes to the contract are known as...?
- A. An appendix to the prime contract
- B. A stand-alone subcontract to the prime contract
- C. An amendment to the prime contract
- D. A separate counter-offer to the supplier
Answer: C
Explanation:
The changes are made to the prime contract. They are also signed and approved by both parties. These changes are known as amendment (variation) to the contract. A contract amendment allows the parties to make a mutually agreed-upon change to an existing contract. An amendment can add to an existing contract, delete from it, or change parts of it. The original contract remains in place, only with some terms altered by way of the amendment.
Reference:
- Modify an Existing Contract with a Contract Amendment
- CIPS study guide page 26-28
LO 1, AC 1.1
NEW QUESTION # 100
A construction company is undertaking a housing development project. They need lots of bricks and other building materials, but the construction site doesn't have large area for storage of materials. Therefore, the company's suppliers must deliver the building materials with fixed quantity and at fixed time intervals. What type of contract is used between the construction company and its suppliers?
- A. Call off contract
- B. Spot transaction
- C. One off contract
- D. Framework agreement
Answer: A
Explanation:
In the scenario, the contract between the company and its suppliers is continuous rather than one-off. So it cannot be one-off contract or spot purchase. The quantity and time is well known and fixed, this type of contract is known as call-off contract or blanket order.
Reference:
LO 1, AC 1.3
NEW QUESTION # 101
In a sale contract, a clause requires the seller to "defend, reimburse, and hold harmless" the buyer and its personnel from and against any and all damages arising in connection with some specific circumstances. This clause is an example of...?
- A. Liquidated damages
- B. Indemnity
- C. Force Majeure
- D. Insurance
Answer: B
Explanation:
An indemnity is a promise by one party to compensate another for the loss suffered as a consequence of a specific event, called the ''trigger event''.
The trigger event can be anything defined by the parties, including:
- A breach of contract;
- A party's fault or negligence;
- A specific action.
An indemnity operates as a transfer of risks between the parties, and changes what they would otherwise be liable for or entitled to under a normal damage claim.
Force Majeure Provisions: A force majeure event refers to the occurrence of an event which is outside the reasonable control of a party and which prevents that party from performing its obligations under a contract.
Liquidated damages are presented in certain legal contracts as an estimate of otherwise intangible or hard-to-define losses to one of the parties. It is a provision that allows for the payment of a specified sum should one of the parties be in breach of contract.
LO 3, AC 3.2
NEW QUESTION # 102
Which of the following are key features of standard terms and conditions? Select TWO that apply
- A. Non-negotiable
- B. Non-disclosure
- C. Standard terms always comply with implied terms
- D. Specific to each purchase order
- E. Designed to be used in repetitive transactions
Answer: A,E
Explanation:
The key features, advantages and disadvantages of standard terms are summarised below:
- Form: Concise, generic and designed to be attached to purchase or sales orders
- Non-negotiable
- Ineffective terms: may be replaced by implied terms or national legal code rules, or subject to court 'balance of interest' judgement.
- Advantages: Basic contractual protection for most common circumstances; Avoid having to create new contract for repeat business.
- User friendly
- Usage: Low value, low risk, repetitive transactions
- Coverage: Definitions, relationship to other contracts, formation of the contract, order of precedence, price, invoicing and payment, specification, legal compliance, warrantee and liability, ownership and risk, intellectual property, data management and ethics.
- Disadvantages: Does not allow for specific circumstances; Risk for creating battle of the forms; Can create contractual uncertainty if used with purchase orders under call-off contracts.
Reference:
LO 3, AC 3.1
NEW QUESTION # 103
Which of the following will always give rise to a claim of misrepresentation?
1. Silence
2. False thought
3. Statement of fact
4. Representation by conduct
- A. 1 and 3 only
- B. 1 and 2 only
- C. 3 and 4 only
- D. 2 and 4 only
Answer: C
Explanation:
A misrepresentation is a false statement of fact or law which induces the representee to enter a contract. Where a statement made during the course of negotiations is classed as a representation rather than a term an action for misrepresentation may be available where the statement turns out to be untrue.
For a party to claim for misrepresentation, there must be a false statement of fact or law as oppose to opinion or estimate of future events. It does not matter whether the incorrect information is given by words or takes the form of misleading conduct.
Silence will not generally amount to a misrepresentation. However, it can become a misrepresentation in some exceptional circumstances.
In the L4M3 study guide, the author states that "A statement of law is not misrepresentation". This is untrue in both common law and civil law systems. In the UK, false statement of law will now amount to an actionable misrepresentation (see Pankhania v Hackney [2002] EWHC 2441).
Reference:
- Misrepresentation
- L4M3 study guide page 53-55
LO 1, AC 1.2
NEW QUESTION # 104
ABC Ltd is a UK based company. It plans to enter into a contract with XYZ Ltd which is based in Singapore. Which of the following are the mandatory elements for the contract between ABC Ltd and XYZ Ltd to be legally binding? Select THREE that apply.
- A. All parties must have capacity to contract
- B. The invitation to tender must be sent by the agreed deadline
- C. There must be an offer and an acceptance
- D. The two parties must have intention to be bound
- E. There must be an invitation to treat
- F. An amount of money must be paid upfront
Answer: C,D
Explanation:
The formation of the contract is where the contractual journey begins; if no contract is formed, neither of the parties can be under any obligations. Therefore, it is very important to have an understanding of each part of a contract's formation.
In order for a legally binding agreement to be formed, there are four basic requirements to be met:
2.1 Offer
2.2 Acceptance
2.3 Certainty & Intention to Create Legal Relations
2.4 Consideration & Promissory Estoppel
Reference:
- CIPS study guide page 28-42
- Formation of the contract
LO 1, AC 1.2
NEW QUESTION # 105
Nestle gave away records of "Rockin' Shoes" or a voucher to people who sent in three wrappers from Nestle's 6d. milk chocolate bars as well as 1s 6d. Which of the following were the consideration of Nestle's customer? Select TWO that apply
- A. Three wrappers
- B. "Rockin' Shoes" record
- C. The voucher
- D. 1s 6d
- E. Milk chocolate bar
Answer: A,D
Explanation:
Consideration is one thing given in exchange for another.
In this case, considerations of customers are three wrappers and 1s6d. Consideration of Nestle is Rockin' Shoes record or a voucher.
Reference:
LO 1, AC 1.2
NEW QUESTION # 106
A construction company often subcontracts approximately 50% of the project works because of unpredictable customer's demand. Although larger corporate customers require quick response to RFQ, the time lapse between tender bid submission and contract commencement is usually long. Which of the following arrangement would benefit both the contractor and customer?
- A. Bilateral contract
- B. Collateral contract
- C. Framework agreement
- D. Indemnity agreement
Answer: C
Explanation:
According to the scenario, customers' demand changes regularly but the construction project commencement often delays. If the contractor and the customer mutually sign a legally binding contract too soon long before the commencement, the contractor may suffer poor cash flow (it must buy the materials first but has to wait for long time to be paid). A framework agreement may help both parties.
A framework agreement is a formal agreement between two organisations that is intended to become legally binding in the event that a contract is created.
A framework agreement could benefit the both parties in the following ways:
- At the time of signing, the framework agreement has not yet become a legally binding contract. The contractor and client only agree on the principles of future contracts (such as whether the work can be subcontracted or how payment will be proceeded). A well structured framework agreement will allow both parties to apply changes before contract commencement, especially regarding price and quality.
- The framework agreement assures a certainty between the contractor and client.
- The administrative works is reduced under a framework agreement.
Reference:
- CIPS study guide page 60-62
- Framework Agreements: Practice and Pitfalls
LO 1, AC 1.3
NEW QUESTION # 107
Cleveland Insurance (Cleveland) offers a range of insurance services. The main software used in the call centre is a customer relationship management (CRM) system. Cleveland perceived an urgent need to replace the existing CRM system to deal with the increasing number of customers and services.
Urgent Digital Ltd (Digital) is one of the bidders of Cleveland's ITT for designing, building and managing the new CRM system. Its bid team is led by Hank Irvine, its technical director. Hank realises that winning the Cleveland contract (valued at approximately £50M) will enhance his career. During discussions with Cleveland, Hank offers certain assurances regarding timescales for the project. He has not carried out any investigations into the viability of the timescales. Hank has little idea whether the timescales can be met.
Cleveland decides that Digital's bid meets with its requirements, especially given the assurances in timescale offered by Hank, and decides to proceed with it, subject to a formal contract. Eventually, a formal contract is signed by both parties. The initial assurances given by Hank about the timing of the project are never going to be achieved and are at best grossly exaggerated.
Cleveland brought the case to the court and sought rescission of contract with Digital. Is Cleveland's claim appropriate in this case?
- A. No, because the contract does not include any provision on rescission
- B. Yes, because Cleveland needs to seek rescission first before claiming for damages
- C. No, because the work had been carried out which could not be returned
- D. Yes, because both parties agreed with rescission of their contract
Answer: C
Explanation:
Hank's pre-contractual assurances may amount to misrepresentation. Remedies for misrepresentation could be rescission of contract or damages. Rescission will be impossible in the following instance:
- Where the innocent party has affirmed the contract; that is, acted in a way confirming that they wish it to continue
- Where the claim has not been brought within a reasonable time (this is a point of general law)
- Where restitution (returning to the pre-contractual position) is impossible (e.g. because the goods have been consumed or have deteriorated)
- Where there has been intervention of innocent third-party (e.g., if the goods have been sold on) In this case, the subject of contract is designing, building and managing the new CRM system which is impossible to be restituted. Therefore, the contract cannot be rescinded.
Reference:
LO 1, AC 1.2
NEW QUESTION # 108
Blakenall District Hospital (BDH) is a large hospital that is a major part of the government's health service. Purchasing staff are in the habit of placing many long-term contracts with suppliers and sub-contractors. Whilst these contracts are usually carried out successfully, prices are often paid that are well over budget. The purchasing manager is concerned to find that, in some cases, members of staff are forcing suppliers to accept fixed price contracts. The policy has caused several problems such as some suppliers refusing to deal with BDH and a few going out of business mid-way through performing a contract with BDH. This is due to fluctuating market prices of materials. The procurement manager suggests supplier to adopt variable pricing arrangement with price index. Is this a right course of action?
- A. No, price adjustment should be applied to short-term supply contract only (3-month duration or less)
- B. Yes, this type of arrangement would provide absolute certainty when budgeting
- C. No, variable pricing would only benefit the suppliers
- D. Yes, this pricing arrangement would reimburse the fluctuation of material prices
Answer: D
Explanation:
Procurement staff in the Hospital is forcing suppliers into fixed price contract. If the costs generally rise, supplier may operate at a loss. This situation can disrupt the relationship, that is the reason why some suppliers refusing to deal with BDH and a few going out of business mid-way.
Alternative methods could be variable pricing arrangement. This method would reimburse the fluctuation of market price. It will also benefit buyer if the market price drops. This type of arrangement should be applied to long-term contracts (i.e. 18 months or more).
Reference:
LO 3, AC 3.3
NEW QUESTION # 109
Which of the following is always automatically considered as a contract?
- A. Performance management framework
- B. Framework arrangement
- C. Call-off
- D. Framework agreement
Answer: C
Explanation:
- A call off or a term contract is one which exists for a fixed period of time, rather than for a specific purpose
- A formal framework agreement does have some legal standing but it is not a contract, primarily because there is no consideration involved, but it is an overarching (or umbrella) agreement under which contracts can be created (this holds true in English law but may not be right in other jurisdiction)
- A framework arrangement is a rather loose set-up, without any legal standing. It usually occurs when an organisation has decided for itself to limit the number of suppliers it is willing to work with and, through a purely internal process, sets up an approved list of such suppliers.
- A performance management framework including KPIs and targets, the assessment scheme and incentives, disincentives, bonuses and penalties. It is a schedule to a contract and only legally binding if it is referred from contract clauses.
Reference:
LO 1, AC 1.3
NEW QUESTION # 110
Which of the following are true statements about RFQ process? Select TWO that apply.
- A. RFQ process is not suitable for low value purchase
- B. Price is often the only variable in the RFQ and quotations
- C. RFQ process requires the suppliers to submit their technical proposals
- D. Buying organisation should only send RFQ to pre-qualified suppliers
- E. RFQ process creates heavier administrative burdens than tendering process
Answer: B,D
Explanation:
Request for quotations is often used when the only variable is price and the purchase value is under a financial threshold. This process is less formal than ITT. RFQ should be used in the following circumstances:
- Low-value, low-risk purchases
- When the specifications are sufficiently defined or the product/service is standardised
- Where the suppliers are pre-qualified
- Where there is a framework agreement which specifies the contract terms and conditions.
Reference:
LO 1, AC 1.1
NEW QUESTION # 111
Is the government only source of industrial standards within a country?
- A. Yes, the standards must be made by legislative branch of the country
- B. No, the government can only adopt standards regarding security and defence
- C. Yes, while ISO make standards for international trade, the government standardises other facets of their country
- D. No, an organisation can also generate its own internal standards
Answer: D
Explanation:
A standard is a document that sets out requirements for a specific item, material, component, system or service, or describes in detail a particular method or procedure. Standards are established by consensus and approved by recognized standardization bodies.
There are several different types of standards. Some of the most commonly-used standards set out the requirements that a particular kind of product, service or process must fulfil, in order to establish that it is 'fit for purpose'. Other types of standard relate to methods of testing, terminology and definitions, information requirements, or the compatibility of connections.
Standards provide individuals, businesses and all kinds of organizations with a common basis for mutual understanding. They are especially useful for communication, measurement, commerce and manufacturing.
Standards make trade easier by ensuring compatibility and interoperability of components, products and services. They bring benefits to businesses and consumers in terms of reducing costs, enhancing performance and improving safety.
Standards are voluntary, which means that businesses and other organizations are not legally obliged to apply them. However, in certain cases standards may facilitate compliance with legal requirements, such as those contained in European directives and regulations.
Standards can be made by a company, a standard organisation (such as ISO or BSI) or regulatory bodies.
Reference:
- CIPS study guide page 93-94
- Standards and your business
LO 2, AC 2.1
NEW QUESTION # 112
......
CIPS L4M3 exam is a crucial assessment for procurement professionals who are looking to advance their career in commercial contracting. L4M3 exam focuses on the skills and knowledge required to successfully manage commercial contracts and ensure effective supplier performance. L4M3 exam covers a wide range of topics, including contract formation, contract administration, and contract termination.
CIPS L4M3 exam is an internationally recognized qualification that is highly valued in the procurement industry. It is designed for individuals who are responsible for managing contracts or involved in the procurement process. As such, it is ideal for procurement professionals who are seeking to develop their careers and enhance their knowledge of commercial contracting. L4M3 exam is also suitable for individuals who work in other areas, such as legal, finance, or project management, and who want to gain a better understanding of contracts and contract management. Overall, the CIPS L4M3 exam is an essential qualification for anyone who wants to excel in the field of procurement and contracting.
Real CIPS L4M3 Exam Dumps with Correct 161 Questions and Answers: https://braindumps2go.dumpsmaterials.com/L4M3-real-torrent.html
